Production Planning
Weekly production planning workflow run by the production planner and operations manager to release work orders, verify materials and capacity, and brief the floor before the production week begins.
Demand and Order Review
-
Pull open sales orders from ERP
Export the open order book from NetSuite, Epicor Kinetic, or Dynamics 365 BC. Filter by promised ship date in the planning horizon (typically the next 4 weeks). Confirm each order has a current rev print and no holds.
-
Reconcile forecast against firm demand
Compare S&OP forecast to firm orders and kanban triggers. Flag any forecast bucket consumed early or under-consumed — those are the signals you'll level-load against in heijunka.
-
Flag at-risk due dates
Compare promised ship date against standard lead time per routing. Any order with insufficient runway gets escalated to customer service same-day for re-promise or expedite.
Collects list -
Notify customer service of at-risk orders
Send the at-risk list to CS with current best-case ship date and the constraint (material, capacity, tooling). CS owns the customer conversation; planning owns the schedule.
Material and Capacity Verification
-
Run MRP and review exception messages
Work the exception queue: reschedule-in, reschedule-out, expedite, cancel. Don't ignore reschedule-out messages — pulling them in clears WIP and frees cash.
-
Verify raw material on-hand against BOMs
Walk the floor on long-lead and high-value items rather than trusting ERP on-hand. Cycle-count variances commonly surface here. Capture lot/heat numbers required for traceability per AS9100 or IATF 16949.
Collects list -
Expedite shortages with purchasing
Buyer contacts supplier for committed delivery date. Document the new promise on the PO. If the supplier can't meet need-by, escalate to second-source on the AVL or notify CS that the WO will slip.
-
Confirm tooling and fixture availability
Check tool crib for required tooling, dies, fixtures, and gauges. Verify gauge calibration is current — a red-tagged past-due gauge will halt FAI. Coordinate with toolroom on any sharpening or repair turnaround.
-
Calculate work-center load against capacity
Compare planned hours per work center to available capacity (shifts × hours × OEE). Identify the constraint resource (CCR) — the schedule must protect the bottleneck per Theory of Constraints. Anything over 90% load is a flag.
Collects list -
Resolve overloaded work centers
Options: add overtime, add a shift, offload to a secondary machine, subcontract, or re-promise the order. Document the decision and the cost impact for ops review.
Schedule Build and Sequencing
-
Sequence work orders by changeover and priority
Apply SMED logic — group by tooling family or material to minimize changeover. Don't sacrifice on-time delivery for setup efficiency on a CCR; protect customer due dates first.
-
Verify routings reflect current ECN status
Cross-check PLM (SolidWorks PDM, Arena, Windchill) for any pending or recently released ECN affecting open WOs. Releasing a job to an old print rev is a common scrap driver — and on regulated work (medical, aerospace) a deviation event.
-
Release the production schedule in MES
Publish the dispatch list in Plex, Tulip, MachineMetrics, or your MES. Each work center gets a sequenced queue with target start/finish times.
-
Stage kits at work centers
Material handlers pull per kit list, verify lot/heat for traceability, and stage at the point of use. Confirm any time-sensitive material (adhesives, plating chemistries) is within shelf life before staging.
Floor Communication and Sign-Off
-
Brief shift leads at production huddle
Walk shift leads through the dispatch list, hot orders, known constraints, and any new ECN training required before run. Use the same gemba board the next shift's handover will use.
-
Confirm operator training for new revs
If an ECN released since last week, verify the assigned operators have signed the training acknowledgment. Running a new rev without trained operators is a common cause of first-piece rejects.
-
Sign off on the weekly production plan
Operations manager reviews the released schedule, capacity assumptions, and at-risk list. Sign-off captures plan-of-record so end-of-week variance review has a baseline.
Collects list Collects paragraph Collects signature
Mid-Week Plan Review
-
Compare actual output to plan
Pull OEE and throughput from MachineMetrics or MES. Identify variance drivers: downtime, scrap, slow cycles, missed setups. Variance under 5% is noise; over that needs a named cause.
-
Adjust schedule for the back half of the week
Re-sequence based on actual progress, not the original plan. If a hot order slipped, decide whether to recover with overtime, swap sequence, or re-promise CS. Document the change so end-of-week review has the trail.
Use this template
Copy it to your account, customize the steps, and run it with your team in minutes.
Browse hundreds of free templates across every team and industry.
Back to template libraryRun Production Planning with your team
Customize the steps, assign roles, set a schedule, and keep a complete record for every run.