Capital Expenditure (CapEx) Approval Checklist

Workflow for evaluating, approving, procuring, and capitalizing a capital expenditure request. Run by the controller or FP&A lead in coordination with the project sponsor, CFO, and procurement.

7 sections 23 steps Collects data
1

Project Evaluation

  1. Define project scope and business case
    • Project sponsor drafts the one-page business case: problem statement, proposed asset, expected useful life, alternatives considered (including lease vs. buy under ASC 842), and the strategic objective served. Tie the request to a numbered line in the approved annual CapEx plan if one exists.

  2. Run a feasibility study with operations
    • Operations lead validates technical feasibility, site requirements, downtime impact, and integration risk. Document show-stoppers (utility capacity, permitting, code compliance) before financial modeling — these often kill projects that look fine on paper.

  3. Draft the project proposal and timeline
    • Proposal includes milestones, project sponsor, accountable executive, target in-service date (drives capitalization start under ASC 360), and a RACI for procurement, finance, and operations.

2

Financial Analysis

  1. Estimate total cost of ownership
    • Build the TCO: purchase price, freight, install, testing, training, plus 5-year operating costs (utilities, maintenance, consumables, software). Separately call out which costs are capitalizable per ASC 360 and which expense as incurred — getting this wrong understates depreciation and overstates Year 1 net income.

    Collects number
  2. Calculate NPV, IRR, and payback period
    • Use the company's published WACC as the discount rate; do not invent a hurdle rate. Show NPV, IRR, payback, and discounted payback. Flag any project where IRR is below hurdle rate but the sponsor still wants approval — those need an explicit strategic-rationale memo.

  3. Build sensitivity and downside scenarios
    • Stress key drivers: revenue uplift -20%, cost overrun +15%, in-service date delayed 6 months. Document where the project breaks even on NPV. Approval committees consistently ask for this; have it ready before the meeting.

3

Budget and Funding Review

  1. Confirm funds in the approved CapEx budget
    • Pull the CapEx tracker (NetSuite, Sage Intacct, or the FP&A workbook). Confirm remaining budget at the cost-center and project-category level. If unbudgeted, flag now — reforecast cycles take 2-3 weeks and will delay approval.

  2. Model balance-sheet and covenant impact
    • Update the rolling forecast: PP&E addition, depreciation expense impact, cash outflow timing, and effect on debt covenants (fixed-charge coverage, leverage ratio, minimum liquidity). Large CapEx within 60 days of a covenant test date is a controller's red flag.

  3. Determine the required approval tier
    • Apply the delegation-of-authority matrix. Typical tiers: under $25K (department head), $25K–$100K (VP), $100K–$500K (CFO), over $500K (CEO + board). Tier drives downstream routing — getting it wrong means the request comes back for re-routing and a missed cycle.

    Collects list
4

Approval Routing

  1. Submit the CapEx package to the approver
    • Package includes business case, TCO model, NPV/IRR/payback summary, sensitivity, budget confirmation, and vendor short-list. Route through the standard CapEx form (AFE — authorization for expenditure) with a unique project number assigned.

  2. Address committee questions and revisions
    • Track every committee question and the revised model version that answers it. Keep a Q&A log appended to the AFE — auditors regularly pull this during ICFR walkthroughs of the CapEx control.

  3. Present to the board of directors
    • Required for projects above the board-approval threshold. Coordinate with the corporate secretary to slot the AFE on the next quarterly board agenda; budget for a 2-4 week wait. Capture board minutes referencing the approved amount — these are the audit evidence.

  4. Capture the final approval signatures
    • Collect signatures on the executed AFE (DocuSign or wet-ink). File in the CapEx project folder; link the document ID to the project number in the GL system so subsequent invoices reference the approved authority.

    Collects file
5

Vendor Selection

  1. Issue an RFQ to qualified vendors
    • Procurement issues to a minimum of three pre-qualified vendors (sole-source justification required if fewer). RFQ includes scope, delivery date, payment terms, warranty, and required insurance certificates.

  2. Score the bids against the evaluation matrix
    • Weighted scoring on price, lead time, technical fit, vendor financial stability, and references. Document the scoring sheet in the project folder; if the lowest bid is not selected, the rationale memo is required for SOX evidence.

  3. Issue the PO to the selected vendor
    • Confirm W-9 on file, COI listing the company as additional insured, and ACH banking details verified by callback to a known number (wire-fraud control). PO references the AFE number and project code.

6

Implementation and Monitoring

  1. Build the implementation plan
    • Project manager builds the Gantt with milestones, owner per milestone, and the cost-tracking baseline. Set up the project in the ERP with a CIP (construction-in-progress) account so invoiced costs accumulate to PP&E rather than expense.

  2. Track actuals against the approved budget
    • Weekly variance report: committed (POs issued), incurred (invoices received), and paid. Compare to AFE budget by category. Three-way match (PO + receiving + invoice) before any vendor invoice posts to CIP.

  3. Confirm whether budget variance exceeds 10%
    • At each milestone, controller reviews cumulative variance vs. AFE. Most delegation matrices require a supplemental AFE if variance exceeds 10% of approved amount — do not let invoices accumulate past that threshold without re-approval.

    Collects list
  4. Escalate the overrun to the CFO
    • Prepare a supplemental AFE memo: cause of overrun, revised total, revised NPV/IRR, and recommendation (continue, descope, cancel). Route through the same approval tier as the original AFE — board projects need board re-approval.

7

Post-Implementation Review

  1. Run the post-completion audit
    • Compare actuals (cost, schedule, realized benefits) to the original AFE 6-12 months after in-service. Internal audit typically owns this; results feed the next year's CapEx-planning calibration.

  2. Document lessons learned
    • Capture what the original model got wrong (revenue ramp, install duration, ongoing maintenance) and update the standard CapEx-template assumptions. Store in the FP&A knowledge base.

  3. Capitalize the asset in the fixed-asset register
    • Reclass CIP balance to the appropriate PP&E sub-account, assign asset class and useful life per the company's capitalization policy, and start depreciation on the in-service date. Confirm tax book (MACRS) is set up alongside GAAP book — divergence is the #1 source of deferred-tax true-up errors at year-end.

    Collects date Collects text Collects number

Use this template

Copy it to your account, customize the steps, and run it with your team in minutes.


Sections 7
Steps 23
Category Accounting
Price Free to start
Need a different process

Browse hundreds of free templates across every team and industry.

Back to template library

Run Capital Expenditure (CapEx) Approval Checklist with your team

Customize the steps, assign roles, set a schedule, and keep a complete record for every run.