Project Closeout Checklist
Steps a commercial GC's project manager runs from substantial completion through financial and document handover. Covers punch list resolution, AHJ final inspections, commissioning, lien waivers, retainage release, and warranty turnover.
Punch List and Substantial Completion
-
Walk the punch list with the architect
Joint walk with the architect, owner's rep, and superintendent. Capture deficiencies room-by-room against the approved drawings and specs. Distinguish punch items from warranty items — punch is incomplete or non-conforming work, not future failures.
-
Distribute punch items to responsible subs
Issue punch list in Procore or ACC with line items assigned to each trade by name and target completion date. Hold daily 15-minute punch huddles until closure; cherry-picking is the most common reason the final 5% never finishes.
Collects file -
Verify punch completion against the drawings
PE or APM verifies each line item in the field with the latest approved drawings and submittal cuts in hand. Don't sign off from a photo — confirm the installed condition matches the approved version, not the original submittal.
Collects list -
Back-charge subs for incomplete items
Issue written notice per the subcontract back-charge clause before bringing in another trade. Document the cure period given, the GC's remediation cost, and apply against the sub's retainage at final pay app.
-
Issue the G704 substantial completion certificate
AIA G704 with attached final punch list, declared date of substantial completion, and listed exceptions. The declared date starts the warranty clock and triggers retainage reduction per the contract — get architect, owner, and GC signatures before circulating.
AHJ Final Inspections and Occupancy
-
Schedule the final building inspection
Confirm all preceding rough and in-wall inspections are signed off in the AHJ portal (Accela or local equivalent) before requesting final. Missing a rough framing or above-ceiling sign-off is a routine reason finals fail or get refused on arrival.
-
Coordinate the fire marshal life-safety walk
Sprinkler contractor witnesses pressure tests, fire alarm vendor demonstrates device-by-device functional matrix, exit signage and egress paths confirmed against NFPA 101. Have stamped shop drawings and the approved fire alarm matrix on hand.
-
Witness elevator and sprinkler acceptance tests
State elevator inspector and fire marshal witness; collect signed certificates of acceptance for the closeout package. Both inspections are common bottlenecks — schedule 4-6 weeks ahead in busy markets.
-
Obtain the TCO or CO from the AHJ
Upload the issued certificate to the project record. A TCO with conditions is acceptable for owner move-in but tracks open items that must clear before full CO; log them with named owners and target dates.
Collects list Collects file -
Resolve outstanding AHJ correction items
Log each correction notice with code citation, responsible trade, and re-inspection date. Submit revised drawings or product data through the AHJ portal where required, then schedule the re-inspection promptly — owner move-in often hinges on it.
Commissioning and Owner Training
-
Complete Cx functional performance tests
Cx authority runs the FPT scripts on HVAC, controls, BMS, and life-safety systems with the MEP subs present. Resolve all Priority 1 issues before owner acceptance; Priority 2 and 3 items roll into the deferred list with target dates.
-
Deliver O&M manuals to the owner
Indexed digital O&Ms with equipment cut sheets, startup reports, control sequences, and maintenance schedules. Cross-reference each entry to the asset tag and the as-built location — facilities staff need to find a unit by tag, not by submittal number.
-
Run owner training on HVAC, fire, and BMS
Live walkthroughs by each major sub at the equipment, with facilities staff attending. Record sessions for staff who turn over after move-in. Capture attendee sign-in sheets for the closeout package.
-
Turn over attic stock and spare parts
Verify quantities against spec section requirements (typical: 2% of installed flooring, ceiling tile, paint by color, light lamps). Owner signs receipt by line item; store in the location designated by facilities.
Financial Closeout
-
Reconcile the final SOV and outstanding CORs
PM and project accountant reconcile the G703 schedule of values against booked costs, executed change orders, and any open CORs. Pending CORs should be either executed, withdrawn, or moved to a claim — they cannot ride open into final pay app.
-
Collect unconditional final lien waivers
Unconditional final waivers from every subcontractor, sub-sub, and material supplier above the state notice threshold. Lower-tier supplier liens are the most common post-closeout surprise — verify against preliminary notices received during the project.
Collects file -
Submit the final pay application with G706 and G707
AIA G702/G703 final, G706 contractor's affidavit of payment of debts and claims, G706A affidavit of release of liens, and G707 consent of surety to final payment. Owner pays only against the complete package; missing G707 is the most common rejection reason on bonded jobs.
-
Release retainage to subcontractors
Release after owner final payment clears and after each sub's unconditional final waiver is on file. Apply any back-charges from punch closure against the retainage balance with written notice to the sub.
Documentation and Handover
-
Compile as-built record drawings
Reconcile field red-lines, RFI responses, ASIs, and bulletins into the architect's CAD or Revit model. Don't reconstruct from memory and phone photos at the end — gaps in below-grade utilities and concealed MEP routing always show.
-
Assemble the warranty package with start dates
Manufacturer warranties, sub workmanship warranties, roofing bond, and any extended warranties keyed to the substantial completion date on the G704. Note any equipment that ran early — its warranty clock may already have started before SC.
-
Deliver the closeout binder to the owner
Indexed digital deliverable: as-builts, O&Ms, warranties, Cx report, training records, attic stock receipt, occupancy certificates, lien waivers, and the final RFI and submittal logs. Confirm the format matches the contract — owner-side facilities groups often require specific structures.
-
Update the project database with final costs
Final cost-to-complete, executed CO total, gross margin, and unit-cost benchmarks tagged for the estimating database. This is what feeds historical cost data for the next bid; skipped here, the next estimator works from memory.
-
Notify stakeholders of project completion
Final notice to owner, design team, lender, surety, and subs confirming closeout. Include the warranty start date, the warranty contact, and the 11-month walk target date so the owner knows when to call the GC back before warranty expiration.
Use this template
Copy it to your account, customize the steps, and run it with your team in minutes.
Browse hundreds of free templates across every team and industry.
Back to template libraryRelated templates
More workflows your team can run.
Run Project Closeout Checklist with your team
Customize the steps, assign roles, set a schedule, and keep a complete record for every run.