Project Quality Control Checklist

Steps a project manager and superintendent run to maintain quality control on a commercial construction project — from ITP approval through submittal review, pre-installation inspections, in-process QC, testing and commissioning, and closeout.

7 sections 30 steps Collects data
1

Pre-Construction QC Setup

  1. Approve the project ITP
    • The Inspection and Test Plan ties each spec section to the inspection points, hold points, witness points, and documentation required. Get owner and architect sign-off before mobilization — retrofitting an ITP after construction starts is how QC programs lose credibility.

  2. Distribute QC plan to trade foremen
    • Each foreman should know which CSI sections govern their scope, which submittals are required before installation, and which inspections are hold points. Post a hard copy in the trailer and load it into Procore for field access.

  3. Schedule pre-installation meetings per CSI division
    • Spec sections often require a pre-installation meeting before the trade starts work — waterproofing, roofing, fireproofing, glazing, flooring, and similar finishes are the usual suspects. Schedule them on the three-week look-ahead so they don't get skipped under field pressure.

  4. Identify required mock-ups and benchmarks
    • Pull every mock-up and benchmark called out in the specs — exterior wall assembly, typical bathroom, brick panel, ceiling grid sample. Assign each to a trade with a target date so the mock-up is built before the production run, not alongside it.

2

Submittal & Material Verification

  1. Log submittals against the spec sections
    • Build the submittal log in Procore from the spec sections — every required shop drawing, product data sheet, sample, and mock-up. A missing line in the log is a missing submittal in the field; reconcile against the table of contents, not just trade memory.

  2. Review mill certifications and product data
    • Match mill certs to the structural spec — yield strength, chemistry, heat numbers — before steel ships. For concrete, verify mix designs against compressive strength, air entrainment, and aggregate requirements. Flag any substitution requests for VE review with the EOR.

  3. Verify submittal approval status
    • Confirm the designer's stamp and any annotations. "Approved as Noted" means order to the noted version, not the as-submitted version — the most common submittal-failure mode is a sub ordering off the original after the designer redlined it.

    Collects list
  4. Inspect deliveries against approved submittals
    • At the gate, verify packing slip, manufacturer, model, and quantity match the approved submittal. Photograph any damage on receipt — once material is staged on site, ownership of damage is hard to assign back to the carrier.

    Collects file
3

Pre-Installation Inspections

  1. Hold the pre-installation meeting
    • Walk the foreman through the spec, the approved submittals, the substrate condition, and the acceptance criteria. Document attendees and decisions in the meeting minutes — the absence of a pre-installation meeting is a frequent owner objection during punch.

  2. Verify layout against control points
    • Field engineer confirms the layout against the established benchmarks and column lines before the trade starts. Layout errors discovered after framing or rough-in are an order of magnitude more expensive to fix.

  3. Inspect the first-article installation
    • Inspect the first unit installed — first window, first bathroom rough-in, first parapet flashing detail — against the spec and the approved submittal. Approving a first-article sets the acceptance benchmark for the rest of the production run.

    Collects list
  4. Issue rework directive to the trade contractor
    • If the first-article failed, issue a written rework directive citing the spec section, the deficiency, and the corrective action required. Halt production on the affected scope until the rework is verified — letting the run continue while "we'll catch it on punch" is how systemic non-conformance is created.

  5. Sign off on the required mock-up
    • Owner, architect, and GC walk the mock-up together and sign the acceptance form. The signed mock-up becomes the visual reference for production work — protect it on site through the duration of the trade's installation.

4

In-Process Quality Control

  1. Walk the site daily with trade foremen
    • Daily QC walk by the superintendent or QC manager, with the foreman of each active trade. Note observations in the daily log — workmanship issues, near-misses, weather impacts. The daily log is evidentiary in delay and differing-site-condition claims.

  2. Log non-conformance reports in Procore
    • Every NCR captures the spec reference, the deficiency, the responsible trade, and the corrective action. A standing weekly NCR review keeps items from aging into closeout disputes; aged NCRs are a leading indicator of a punch list that won't close.

    Collects paragraph
  3. Verify rework completion before cover-up
    • Before any in-wall, above-ceiling, or below-grade work is covered, the QC manager verifies that NCRs against that scope are closed. Once it's behind drywall or under slab, you're paying twice to fix it.

  4. Coordinate special inspections with the agency
    • Per IBC Chapter 17, special inspections cover structural welds, post-installed anchors, high-strength bolting, fireproofing, and similar items. Schedule the third-party agency in advance — agencies booked at the last minute miss the pour or the bolt-up window, and the work has to be uncovered.

5

Testing & Commissioning

  1. Witness 7-day and 28-day cylinder breaks
    • Confirm the testing lab's cylinder set covers each pour, that 7-day breaks are trending toward design strength, and 28-day results meet ACI 318 acceptance criteria. Low breaks trigger ACI 318 §26.12 evaluation — core sampling, load testing, or reinforcement analysis.

  2. Witness MEP pressure and flushing tests
    • Hydrostatic tests on domestic water and waste lines, pressure tests on medical gas and refrigerant piping, duct leakage tests on supply and return systems. Witnessed tests with signed forms — verbal sign-off doesn't survive an owner challenge during closeout.

  3. Coordinate Cx authority for system startup
    • The commissioning authority witnesses startup, functional performance testing, and integrated system testing per the Cx plan. Skipping commissioning is the most common reason a TCO'd building shows up in the warranty period with HVAC complaints.

  4. Archive test results and inspection reports
    • Compile every test report, special inspection letter, and Cx report into the closeout package. The owner's facilities team will reference these in year one — if they aren't archived now, they're effectively lost.

    Collects file
6

Punch List & Closeout

  1. Generate punch list with named owner per item
    • Walk the building with the architect and owner. Every item gets a responsible trade, a target completion date, and a location reference. Punch lists without named owners drift; the last 5% of work is where retainage gets stuck.

  2. Confirm punch list closure status
    • Re-walk every item with the architect. Sign-off requires verification — "the sub said it's done" is not closure. Items remaining trigger a follow-up walk, not an extension by default.

    Collects list
  3. Schedule the follow-up punch walk
    • If items remain open, schedule the next walk within a week and notify the responsible trade in writing. Track aged punch items in the OAC meeting until closed; aged items past 30 days trigger back-charge review.

  4. Collect final lien waivers from subs
    • Unconditional final waivers from every sub, sub-sub, and supplier of record before retention release. A missed waiver from a lower-tier supplier is the most common source of a post-closeout lien on the owner's title.

  5. Issue the G704 substantial completion
    • AIA G704 establishes the substantial completion date that starts the warranty clock and shifts insurance and utilities to the owner. Architect, owner, and contractor all sign — and the punch list is attached as the schedule of incomplete work.

7

Project Archive & Lessons Learned

  1. Compile as-built record drawings
    • Reconcile field redlines maintained throughout the job against the contract drawings. As-builts produced from memory at closeout have gaps; weekly redline maintenance during construction is the only way to deliver accurate records.

  2. Deliver O&M manuals and warranty packages
    • Equipment O&M manuals, attic stock inventory, manufacturer warranties, and the contractor's one-year warranty letter. Owner training sessions on major systems should be recorded and indexed in the closeout package.

  3. Lead the lessons-learned meeting
    • Project team reviews what worked, what didn't, and where the QC plan needs revision. Capture concrete items — submittal turnaround issues with specific designers, recurring NCR categories, sub performance — not generic platitudes.

  4. Archive the project in the document system
    • Final archive in Procore or ACC: contract documents, RFI log, submittal log, NCR log, daily logs, meeting minutes, test reports, as-builts, warranty package, and closeout correspondence. The archive is the reference set for warranty calls and any future litigation.

Use this template

Copy it to your account, customize the steps, and run it with your team in minutes.


Sections 7
Steps 30
Category Construction
Price Free to start
Need a different process

Browse hundreds of free templates across every team and industry.

Back to template library

Run Project Quality Control Checklist with your team

Customize the steps, assign roles, set a schedule, and keep a complete record for every run.