Punch List Checklist
Substantial-completion punch list workflow run by the GC's project engineer and superintendent with the architect and owner's rep. Walks the building room-by-room, logs deficiencies by trade, drives subs to closure, and clears the list for certificate of substantial completion...
Pre-Walk Preparation
-
Confirm trades have completed self-punch
Each subcontractor foreman walks their own scope first and clears obvious defects before the architect's walk. Pre-walk by the GC super weeds out items that should never have hit the formal list — missing escutcheons, unpainted touch-ups, debris in fixtures.
-
Pull current drawings and approved submittals
Use the latest bulletin/ASI set, not the bid set. Approved submittals (finishes, hardware, fixtures) are the reference for what was supposed to be installed — punch items get rejected when the walker calls out a finish that matches an early submittal but not the as-approved revision.
-
Set up the punch list in Procore or PlanGrid
Configure the punch list tool with rooms, trades, and responsible subs pre-mapped to scope. Photo-capture and location pins on the floor plan are non-negotiable — "door doesn't close right" without a room number and a pin is a punch item that never closes.
-
Schedule the architect and owner walk
Architect, owner's rep, GC PM, and super attend. MEP engineer joins for a half-day of mechanical/electrical room walks. Confirm the walk happens after the GC's pre-walk is closed — bringing the architect into a building full of obvious defects burns goodwill and stretches the schedule.
Architect and Owner Walk
-
Walk the building floor-by-floor with the architect
Move systematically — typically top-down or by stack — so no rooms get skipped. Tag each item with room number, trade, photo, and description. Items that are scope changes or owner additions get flagged separately as PCO candidates rather than punch.
-
Log architectural finish deficiencies
Drywall pops, paint touch-ups, ceiling tile alignment, millwork joints, flooring transitions, door hardware operation, casework reveals. Reference the approved finish schedule when calling out paint sheen or wall-base profile mismatches.
-
Log MEP and life-safety deficiencies
Diffuser alignment, thermostat location, light-fixture lensing, sprinkler escutcheons, exit-sign visibility, fire-extinguisher mounting heights per NFPA 10, ADA-mounting compliance for switches and devices. Coordinate with the commissioning agent's findings — don't double-list Cx items as punch.
-
Capture punch list exportCollects file
Distribution and Sub Acceptance
-
Sort items by responsible subcontractor
Each item gets one named sub. Items that span trades (drywall patch in a wall the electrician opened) get a primary sub and a coordination note. Disputed assignments — "that's not our scope" — get escalated to the PM with the subcontract scope sheet, not negotiated by the super on the fly.
-
Issue punch list to subs with target completion dates
Standard target is 14 calendar days for most punch items, longer only for items with material lead times (replacement doors, custom millwork). Send via Procore or email-to-Procore so the issuance date is logged for retention disputes later.
-
Confirm sub acknowledgment of assigned itemsCollects list
-
Escalate non-responsive subs to bond or default
If a sub has not acknowledged or scheduled their punch within five days of issuance, send a written cure notice per the subcontract default provisions. For bonded subs, copy the surety on the cure notice — late surety notification is a common reason performance-bond claims get denied.
Item Closure and Verification
-
Track daily progress in the punch log
Super reviews open items each morning at the daily huddle. Aged items (more than 7 days open past target) are called out by sub with a recovery commitment. Don't let "in progress" mask a stalled item — require a date, not a status.
-
Re-walk completed items with the GC superintendent
Super verifies each "complete" item before flipping it for architect re-walk. Subs marking their own items closed without GC verification is the leading cause of re-walks running 3+ rounds. Photo of the corrected condition attached to each item.
-
Hold architect re-walk for verification
Architect signs off on items the GC has marked verified. Items rejected on re-walk reset to open with a note from the architect on what's still wrong — common reasons are wrong paint sheen, transition strip not flush, hardware backset off.
-
Confirm punch list closure statusCollects list Collects number Collects paragraph
Recovery for Open Items
-
Issue back-charge notices for unresolved items
For items the original sub will not complete, issue a written back-charge notice per the subcontract before having another trade complete the work. Document the corrective scope, hours, and materials so the back-charge survives a dispute at retention release.
-
Self-perform or reassign open scope
GC field crew or a replacement sub completes the work. Track time and materials separately under a back-charge cost code so the deduction from the original sub's final pay app is clean.
-
Re-verify recovery work with the architect
Recovery items go back through the same architect re-walk process. Don't let recovery work bypass verification — the standard for substantial completion is the same regardless of who corrected it.
Substantial Completion and Closeout
-
Issue AIA G704 certificate of substantial completion
G704 names the date of substantial completion, attaches the final punch list as the deficiency exhibit, and starts warranty clocks. Owner, architect, and GC all sign. The date matters — it triggers warranty start, retention reduction, and (often) liquidated-damages cutoff.
-
Collect final unconditional lien waivers
Final unconditional waiver from every sub, sub-sub, and supplier on the project before retention release. Releasing retention without a complete waiver set leaves the owner exposed to a lien from a lower-tier claimant — a common, expensive closeout failure.
-
Submit closeout package
As-builts (record drawings), O&M manuals, warranty letters, attic stock receipts, training sign-offs, commissioning report, final inspection sign-offs from AHJ, certificate of occupancy. Punch list closure log is part of the package as evidence the building was delivered to spec.
Collects file -
Process retention release pay application
Final AIA G702/G703 with retention release, G707 consent of surety, and the unconditional final waiver set. Confirm any back-charges from punch recovery are reflected as deductions on the responsible subs' final billings before the GC's own retention is released by the owner.
Use this template
Copy it to your account, customize the steps, and run it with your team in minutes.
Browse hundreds of free templates across every team and industry.
Back to template libraryRelated templates
More workflows your team can run.
Run Punch List Checklist with your team
Customize the steps, assign roles, set a schedule, and keep a complete record for every run.