Contract Management Checklist
Workflow a project manager and contracts lead at an engineering consulting firm run from agreement execution through closeout — covering AIA / EJCDC / ACEC agreements, professional liability terms, scope changes, and record retention.
Contract Setup & Negotiation
-
Pull the appropriate agreement template
Use AIA B-series for owner-architect / engineer agreements, EJCDC E-500 for owner-engineer on infrastructure work, or the ACEC contract guide for prime engineering. Avoid signing the client's bespoke form without legal review — owner-drafted contracts often strip the standard limitation of liability and reciprocal indemnity provisions.
-
Confirm scope, fee basis, and reimbursables
Distinguish basic services from additional services in writing. Lump sum vs. cost-plus vs. T&M each have different change-order triggers — make sure the fee basis matches how the PM intends to track the work in Deltek or Ajera.
-
Review limitation of liability and indemnity clauses
Check the LoL cap (commonly fee or a fixed dollar amount), mutual waiver of consequential damages, and that the indemnity is limited to the engineer's negligence — not a broad duty-to-defend. Flag any clause that triggers coverage outside the firm's professional liability policy for legal review.
-
Verify insurance requirements against carrier limits
Confirm professional liability, CGL, auto, and umbrella limits in the contract match what the firm actually carries. Owner additional-insured language on the PL policy is a common rejection — most claims-made E&O policies do not allow it. Request COIs from the broker before signing.
-
Negotiate redlines with the client
Track every redline round in a single comparison file. Common negotiation points: standard of care wording, ownership of instruments of service, betterment exclusion, statute of repose alignment with state law, and termination-for-convenience notice period.
-
Execute the signed agreement
Capture the fully countersigned PDF, the contract type, and the effective date so downstream invoicing, schedule, and statute-of-repose tracking pull from one source of truth.
Collects list Collects file Collects date
Project Setup & Records
-
Open the project in Deltek and assign charge codes
Set up phases, tasks, and labor categories in Deltek Vantagepoint or Ajera to mirror the contract's fee breakdown. Wrong charge-code structure at setup is the most common reason invoices get kicked back during the first billing cycle.
-
Upload the executed contract to the CDE
File the agreement, COIs, and any addenda in the project's ProjectWise or Newforma record under the contracts folder. The unsigned working drafts should be moved to an archive folder so future RFI / claims work can't reference superseded text.
-
Brief the project team on contract terms
The PM walks the design team through scope boundaries, deliverable list, submittal turnaround commitments, and additional-services triggers. Designers and EITs need to know which client requests to flag rather than absorb into basic services.
Performance & Invoicing
-
Track scope, schedule, and fee at each milestone
At every milestone (30% / 60% / 90% / IFC), run the project's earned-value report against the contract fee. Realization rate slipping below 0.95 by 60% almost always signals scope creep that should have been a change order.
-
Log additional-services requests separately
When the client asks for work outside basic services (added alternates, re-design after owner program changes, accelerated submittal), open a separate task code immediately. Charging additional services to the basic-services budget without written authorization is the leading cause of fee disputes at closeout.
-
Determine whether a contract amendment is needed
Material scope or fee changes require a written amendment, not an email confirmation. Verbal authorizations from the owner's project manager rarely survive a claim — get the amendment routed before incurring the cost.
Collects list -
Issue the contract amendment for signature
Use the same form family as the prime agreement (AIA G802, EJCDC E-505, or the ACEC equivalent). Reference the original contract by date and effective date, describe the scope delta, the fee delta, and the schedule impact. Do not start the added work until the amendment is countersigned.
-
Reconcile monthly invoices against contract terms
Match labor categories, multipliers, and reimbursable markups against the agreement before the invoice goes out. Prompt-pay statutes in most states limit how long the owner can hold a properly-formatted invoice — formatting errors restart the clock.
Disputes & Risk
-
Document disputed deliverables in the issue log
When the owner pushes back on a sealed deliverable, calc set, or RFI response, capture the disagreement in writing immediately — date, who said what, the engineer's position grounded in code or standard of care. Reconstructing this conversation 18 months later from memory is how E&O claims grow.
-
Assess breach exposure with the PIC and counsel
The PIC and the firm's risk manager (and outside counsel if warranted) classify the exposure. High exposure typically means an alleged design defect, missed code requirement, or owner-asserted damages exceeding the LoL cap. Most state professional liability policies require notice of a potential claim — not just an actual claim — within the policy period.
Collects list -
Notify the professional liability carrier
Claims-made policies require notice within the policy period — late notice is itself grounds for denial of coverage. Send notice through the broker per the policy's reporting clause; do not admit liability or offer remediation work without carrier coordination.
Closeout & Archival
-
Confirm final deliverables have been accepted
Verify the owner has accepted the IFC drawings, record drawings, calc packages, and any closeout submittals required by contract. Outstanding deliverables held against the final invoice are a frequent collection blocker.
-
Reconcile final invoice and unbilled time
Pull the WIP report from Deltek; close out unbilled labor and reimbursables before submitting the final invoice. Anything left in WIP after project closure typically gets written off against the project's profit.
-
Prepare the closeout memo and lessons learned
Capture realization rate vs. plan, change orders issued, RFI volume, claims or disputes, and design issues for the practice's lessons-learned database. This is the input that improves fee estimates on the next pursuit.
Collects file Collects paragraph -
Archive contract per the retention policy
Move the executed contract, amendments, sealed deliverables, calc packages, and correspondence to long-term archive. Most states' statute of repose runs 6-12 years from substantial completion — retention must outlast it. Native CAD / Revit models go to cold storage with the project's date-stamped seal version locked.
-
Decide on renewal or formal termination
Master service agreements with rolling task orders typically renew annually; one-off project contracts terminate at substantial completion plus the warranty period. Send the formal termination or renewal notice per the agreement's notice clause — not by email — so the record is clean.
Collects list
Use this template
Copy it to your account, customize the steps, and run it with your team in minutes.
Browse hundreds of free templates across every team and industry.
Back to template libraryRelated templates
More workflows your team can run.
Run Contract Management Checklist with your team
Customize the steps, assign roles, set a schedule, and keep a complete record for every run.