Energy Efficiency Audit Checklist
Steps an energy auditor or facility manager runs to assess a manufacturing plant's electricity, gas, and compressed air consumption, identify ECMs (energy conservation measures), and build a CAPEX-ready findings report. Aligned to ASHRAE audit levels 1–3.
Audit Preparation
-
Pull 24 months of utility bills
Request electricity (kWh and demand kW), natural gas (therms or MMBtu), and any purchased steam or water bills covering at least the last two full years. Two years lets you separate weather-driven swings from real consumption changes. Capture rate schedule, demand charges, and any time-of-use windows — these drive the savings math later.
Collects file -
Set the ASHRAE audit level and scope
Confirm with the plant manager whether this is a Level 1 walkthrough (visual + bill analysis), Level 2 energy survey (measurement + ECM list with simple payback), or Level 3 detailed analysis (calibrated energy model + life-cycle costing). Level drives effort, instrumentation, and report depth.
Collects list -
Schedule the on-site walkthrough
Coordinate with the plant manager and maintenance lead. Plan the visit to cover at least one full production shift plus a non-production interval — leak quantification and standby-load measurements both require the plant to be idle.
-
Gather one-line diagram and equipment list
Pull the electrical one-line, mechanical drawings, and the equipment master from CMMS (Fiix, eMaint, Maximo, or whatever's in use). You need motor HP, RTU and chiller tonnage, compressor capacity, oven/furnace setpoints, and operating schedules before you walk the floor.
Building Envelope and Lighting
-
Inspect envelope, roof, and dock seals
Look for failed dock seals, gaps under personnel doors, missing strip curtains between conditioned and unconditioned space, and roof insulation in poor condition. Dock leakage is the most commonly missed envelope loss in plants with frequent truck activity.
-
Inventory lighting fixtures and run hours
Count fixtures by type (T8, T5HO, metal halide, high-pressure sodium, existing LED), wattage, and area served. Capture annual operating hours by zone — production floor often runs 4,000–6,000 hours; warehouse and office run far less. Hours drive the kWh savings, not just wattage.
-
Test occupancy and daylight controls
Walk warehouse aisles, restrooms, mechanical rooms, and break rooms with the lights off and confirm sensors trip correctly. Disabled or bypassed sensors are common — operators get tired of working in the dark and someone tapes over them.
-
Photograph LED retrofit candidates
Capture mounting type, height, and ballast condition for each fixture group. The retrofit kit decision (lamp-and-ballast vs. full fixture replacement) depends on the existing housing — photos save a return trip.
Collects file
HVAC and Compressed Air
-
Survey RTUs, chillers, and air handlers
Record nameplate tonnage, age, refrigerant type, and EER/SEER where listed. Note economizer presence and whether dampers actually modulate (stuck economizers are a top-three HVAC finding). Confirm setpoints and schedules against actual occupancy.
-
Log compressed air pressure and schedule
Read header pressure at the compressor and at the farthest end-use. A drop greater than 10 psi means a piping or filter restriction. Confirm whether compressors run during off-shifts — running 168 hours/week to feed a Monday-through-Friday plant is a giant leak bill.
-
Quantify compressed air leaks during off-shift
With production stopped, measure leak load by pump-up test (time to fill the receiver) or use an ultrasonic detector to tag leaks. Industry rule of thumb: untagged plants run 25–35% leak rate. Each 1 cfm of leak at 100 psi costs roughly $200/year at $0.10/kWh.
-
Verify VFDs on fans, pumps, and compressors
Confirm variable-speed drives are actually modulating — VFDs running pinned at 60 Hz with a downstream throttle valve are doing nothing. Check controller programming and any bypass that was added during a past breakdown and never reverted.
Process Equipment and Motors
-
Inventory motors over 5 HP with NEMA class
Capture HP, RPM, service factor, voltage, and NEMA efficiency class (Standard, Energy Efficient, Premium, IE3, IE4). Older Standard-class motors above 25 HP running 6,000+ hours/year are usually the strongest premium-motor replacement candidates — and most utilities rebate them.
-
Review oven and furnace idle schedules
Check whether ovens, batch furnaces, and curing chambers actually shut down or setback between shifts. "It takes too long to come back up" is the standard pushback — the audit should test that claim against measured warm-up time and propose interlock with the production schedule.
-
Assess heat recovery opportunities
Compressor jacket heat, oven exhaust, and process cooling water are the three usual sources. Match against demand: makeup air heating, domestic hot water, or boiler feedwater preheat. A 100 HP compressor rejects roughly 250,000 BTU/hr that is almost always vented to outside.
Findings, ROI, and Reporting
-
Build a calibrated energy model
Required for ASHRAE Level 3. Build the model in eQUEST, EnergyPlus, or equivalent and calibrate against the 24 months of utility data — CV(RMSE) under 15% monthly is the ASHRAE Guideline 14 target. The model lets you stack interactive ECMs without double-counting savings.
-
Calculate kWh and therm savings per ECM
For each ECM, list installed cost, annual energy savings (kWh and therms), demand reduction (kW), simple payback, and dollar savings at the plant's actual blended rate — not the headline residential rate. Stack measures in the order the customer would implement, so interactive effects (lighting reducing cooling load) aren't double-counted.
Collects paragraph -
Confirm utility rebate eligibility
Check the serving utility's prescriptive and custom incentive programs. Most utilities require pre-approval before equipment is purchased — installing first and applying after disqualifies the project. Capture the rebate amount per ECM in the savings worksheet.
Collects list -
File rebate pre-approval applications
Submit the utility's pre-approval forms with quantity, model, and efficiency documentation per ECM. Track the application number — utilities reserve the funds against your application, and rebate budgets do run out late in the program year.
-
Present findings to plant leadership
Walk the plant manager and controller through the ECM list ranked by simple payback. Capture which measures are approved for CAPEX, which are deferred, and which are killed — leadership sign-off is what turns the audit into action. Attach the signed report to the project record.
Collects list Collects paragraph Collects signature
Use this template
Copy it to your account, customize the steps, and run it with your team in minutes.
Browse hundreds of free templates across every team and industry.
Back to template libraryRun Energy Efficiency Audit Checklist with your team
Customize the steps, assign roles, set a schedule, and keep a complete record for every run.