Manufacturing Project Planning Checklist
A planning workflow for new product introduction (NPI) and capital projects in a manufacturing plant — covering scope, PFMEA, budget, AIAG-style quality planning, and capacity verification before production release.
Project Scope and Charter
-
Confirm customer program and scope
Capture the customer name, program identifier, target SOP date, and annual volume forecast. Pull the customer's RFQ and any design records — incomplete scope at this step is the most common reason NPI launches slip.
Collects text -
Define PPAP submission level
Level 3 is the AIAG default; automotive customers often require Level 4 or 5 for safety-critical features. The level drives which 18 PPAP elements you owe at submission — get this wrong and the customer rejects the launch package.
Collects list -
Document deliverables and acceptance criteria
List every deliverable the customer expects at PPAP: control plan, PFMEA, MSA, capability study, dimensional results, material certs, appearance approval. Tie each to a named acceptance criterion so the program manager can sign off cleanly at the gate.
-
Set program gate reviews
Lock dates for the kickoff, design freeze, tooling release, run-at-rate, and PPAP submission gates. Assign a gatekeeper per gate and define the exit criteria — gates without exit criteria become rubber-stamp meetings.
-
Publish stakeholder communication cadence
Weekly status to the customer program manager, daily stand-up on the floor, monthly steering review for leadership. Name the owner and channel for each cadence.
Risk Assessment and FMEA
-
Conduct PFMEA on the process flow
Walk every operation in the routing with the cross-functional team — manufacturing engineer, quality, operator, maintenance. Score severity, occurrence, and detection per AIAG-VDA; flag any RPN above the customer's threshold for mandatory mitigation.
-
Review DFMEA inputs from engineering
Pull the DFMEA from the design team and identify any failure modes that the process must detect or prevent. Closing the DFMEA-to-PFMEA loop is the most common gap auditors flag in IATF 16949 surveillance.
-
Build the risk register with RPN scores
Attach the consolidated risk register covering process, supply chain, tooling, and ramp risks. Each row needs a current RPN, a target RPN, and a planned mitigation.
Collects file -
Assign mitigation owners for top RPN items
Every high-RPN item gets a named owner with a due date — usually the manufacturing engineer, supplier quality engineer, or maintenance manager depending on the failure mode. Unowned mitigations sit untouched until launch.
-
Schedule FMEA review checkpoints
PFMEA is a living document. Schedule reviews after pilot run, after run-at-rate, and any time an ECN changes the process. Process-changes-without-PFMEA-update is a classic IATF non-conformance.
Budget and Capital Planning
-
Estimate tooling and fixture costs
Quote dies, molds, fixtures, gauges, and any custom end-effectors. Build in 10–15% contingency for tooling tryout and rework — first-shot tooling rarely runs to print.
-
Quote capital equipment and validation
Capture machine quotes, install costs, utility hookups, and IQ/OQ/PQ validation effort. For regulated product (medical, food contact, aerospace), validation can equal 30–50% of the equipment cost — don't underestimate it.
-
Build the project budget and cash flow
Roll tooling, capital, prototype material, validation labor, and outside services into a phased budget aligned to the gate schedule. Show monthly cash needs so finance can fund without surprises.
-
Submit AFE for capital approval
Route the Authorization for Expenditure through the approval chain — typically plant manager, controller, VP manufacturing, and CFO above threshold. Attach the signed AFE so procurement can release tooling POs without re-litigating the spend.
Collects file -
Define cost variance reporting cadence
Set a weekly burn-rate review against the AFE baseline. Flag any line item tracking >5% over and route to the program manager — early flags get corrective action; late flags become surprises at gate review.
Quality Planning
-
Draft the control plan per AIAG format
One row per characteristic per operation: spec, gauge, sample size, frequency, reaction plan. Pull the special characteristics list from the customer drawing — missing a customer-designated SC at PPAP is an automatic rejection.
-
Confirm AS9102 first-article requirement
Aerospace and defense customers typically require AS9102 Form 1/2/3 at first article. Some commercial customers waive the AS9102 format and accept a customer-specific FAI form. Confirm with the customer quality contact before planning the FAI activity.
Collects list -
Schedule AS9102 first-article inspection
Plan the bubbled drawing, ballooned print, and AS9102 Forms 1, 2, and 3 for the first production run. CMM time on critical features needs to be booked early — CMM queue is the most common bottleneck at FAI.
-
Plan gauge R&R for critical characteristics
Run a 10-part, 3-operator, 3-trial study per AIAG MSA-4 on every customer-designated SC. Target %GR&R below 10% for critical, below 30% for acceptable. Failing gauges block the capability study downstream.
-
Define ANSI Z1.4 sampling for in-process checks
Pick the inspection level (typically II) and AQL per characteristic class — tighter for safety, looser for cosmetic. Document the switching rules between normal, tightened, and reduced inspection so the floor knows when to escalate.
Resource and Capacity Planning
-
Map operations to work centers and takt
For each routing operation, assign the work center and compare cycle time to takt. Any operation where cycle time exceeds takt is a planned bottleneck — either rebalance, add a parallel station, or invest in faster equipment.
-
Build operator skills matrix and training plan
List every operation, the operators qualified to run it, and the gap to staff three shifts at full ramp. Cross-train at least two operators per critical station — single-operator dependency kills launch ramp.
-
Verify capacity meets customer takt
Run a capacity model at PPAP volume and at peak forecast. Account for OEE assumptions — 65–75% is typical for new processes, not the 85% planners often assume. If actual capacity sits below customer demand, flag No here so the expansion plan triggers.
Collects list -
Develop the capacity expansion plan
Lay out the path to close the capacity gap: added shift, parallel cell, outside processing, or capital. Each option needs cost, lead time, and risk so the steering review can pick before the gap impacts customer ramp.
-
Lock the production schedule baseline
Publish the baseline schedule in the ERP/MES — pilot run, run-at-rate, PPAP build, ramp curve. Baseline becomes the reference for variance reporting; changes after this point require a documented program manager approval.